Cost Escalation Tracker
Track material and labour cost escalations against your frozen BOQ — with risk alerts, approval workflow, category breakdown, and client-facing summary PDF.
Project Controls
Baseline Value
₹8,88,950
frozen BOQ
Current Value
₹9,22,400
after approved changes
Total Escalation
₹59,250
+3.8% of baseline
Contingency Buffer
₹88,895
10% of baseline
4 Approved2 Pending0 Rejected2 CriticalApproved: ₹33,450 · Pending: ₹25,800
Category Escalation Breakdown
| Category | Base Cost | Total Impact | Approved | Esc % | Count |
|---|---|---|---|---|---|
| Wardrobe | ₹4,04,000 | ₹24,300 | — | +6.0% | 1 |
| Kitchen | ₹2,38,750 | ₹20,450 | ₹20,450 | +8.6% | 2 |
| Electrical | ₹83,600 | ₹7,600 | ₹7,600 | +9.1% | 1 |
| Paint | ₹39,600 | ₹5,400 | ₹5,400 | +13.6% | 1 |
| Ceiling | ₹35,000 | ₹1,500 | — | +4.3% | 1 |
| Living | ₹88,000 | — | — | +0.0% | 0 |
Escalation Reason Analysis
Specification Upgrade1 entry
₹24,30041.0%
Material Price Rise1 entry
₹18,00030.4%
Design Revision1 entry
₹7,60012.8%
Vendor Change1 entry
₹5,4009.1%
Transport/Logistics1 entry
₹2,4504.1%
Timeline Delay1 entry
₹1,5002.5%
Contingency Buffer Status
Used ₹33,450 of ₹88,895 contingency